 Vancouver, British Columbia: Roca Mines Inc. (ROK: TSX-V) ("Roca" or "the Company") announces the following update on activities at its MAX Molybdenum Mine.

Roca's third primary diesel genset arrived on Wednesday September 5, 2007 and is being load tested together with the two other units. Once completed, the mine/mill power distribution system will be energized and various rental genset units used during construction will be phased out.

The jaw crusher has successfully completed the first phase of testing with no significant problems identified; minor adjustments will be made prior to testing the completed crusher facility. The cone crusher and associated conveyors will be similarly tested over the coming days. As described previously, initial testing of the crusher facility will use waste rock and low-grade material leading to the crushing of stockpiled ore-grade material located nearby.

By mutual agreement, the Company announces the termination of its consulting agreement with Mr. John Kiernan, P. Eng. as its Vice President, Mining effective September 7, 2007.



ROCA MINES INC.
"Scott Broughton"

Scott E. Broughton, P.Eng. -- President & CEO


For further information contact:
Doug Fosbrooke
Investor Relations
Tel: 604-684-2900
Fax: 604-684-2902
Email: [email protected]
Web: www.rocamines.com

The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this release.
 
 

You can view the Next News Releases item: Mon Oct 29, 2007, ROCA - Production Commences at MAX Molybdenum Mine

You can view the Previous News Releases item: Tue Sep 4, 2007, ROCA - MAX Molybdenum Mine Construction Update

You can return to the main News Releases page, or press the Back button on your browser.